Crystal Cove Ct, McKinney: permits on record
6 home-service permits on record on Crystal Cove Ct since February 4, 2025, 6 of them since October 1, 2024, at 5 addresses. Home-service permits only (roofing, heating and cooling, solar, electrical, plumbing, water heaters); other building permits are kept in the record and not shown. Permits are listed without house numbers; each address has its own page below.
Roofing: 1 permit
From Dec 11, 2025 to Dec 11, 2025. Fewer than 5 roofing permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN.
| Issued | Work | Building | Declared value | Contractor as filed | Permit |
|---|---|---|---|---|---|
| Dec 11, 2025 | Roof/Re-Roof: RE-ROOF PER CMC DEC 2025 PERMIT REPORT | Residential | $40,000 | NOT GIVEN | 25-12-06114 |
Heating and cooling: 3 permits
From Feb 4, 2025 to Oct 3, 2025. Fewer than 5 heating and cooling permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN (3).
| Issued | Work | Building | Declared value | Contractor as filed | Permit |
|---|---|---|---|---|---|
| Oct 3, 2025 | Miscellaneous: INSTALLATION OF HVAC SYSTEM PER CMC OCTOBER 2025 PERMIT REPORT | Residential | $21,400 | NOT GIVEN | 2025-10-05103 |
| Mar 14, 2025 | Miscellaneous: HVAC - REPLACE COMPLETE PER CMC MARCH 2025 PERMIT REPORT | Residential | $15,320 | NOT GIVEN | 25-03-01186 |
| Feb 4, 2025 | Miscellaneous: MECHANICAL- REPLACE COMPLETE HVAC SYSTEM PER 2/25 PERMIT REPORT | Residential | $28,856 | NOT GIVEN | 25-02-00512 |
Solar: 1 permit
From Apr 7, 2026 to Apr 7, 2026. Fewer than 5 solar permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN.
| Issued | Work | Building | Declared value | Contractor as filed | Permit |
|---|---|---|---|---|---|
| Apr 7, 2026 | Solar Energy Device: ROOF MOUNTED SOLAR PER CMC APR 2026 PERMIT REPORT | Residential | $46,950 | NOT GIVEN | 26-03-00027 |
Electrical: 1 permit
From Aug 18, 2025 to Aug 18, 2025. Fewer than 5 electrical permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN.
| Issued | Work | Building | Declared value | Contractor as filed | Permit |
|---|---|---|---|---|---|
| Aug 18, 2025 | Miscellaneous: NEW OUTDOOR GRILL STRUCTURE WITH GAS AND ELECTRIC, PER AUG 2025 CMC PERMIT REPORT | Residential | $7,500 | NOT GIVEN | 25-08-04034 |