Permits Index
3
Permits, 24 months
5 on record
1
Roofing permits
Jun 4, 2026
Last permit issued
4
Addresses with a page

Roofing: 1 permit

From May 27, 2025 to May 27, 2025. Fewer than 5 roofing permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT LISTED.

IssuedWorkBuildingDeclared valueContractor as filedPermit
May 27, 2025Roof/Re-Roof: PER MAY 2025 MCKINNEY PERMIT REPORT: REROOFResidential$19,000NOT LISTEDRES2025-05-02598

Solar: 3 permits

From Jun 13, 2024 to Oct 24, 2025. Fewer than 5 solar permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN (3).

IssuedWorkBuildingDeclared valueContractor as filedPermit
Oct 24, 2025Solar Energy Device: SOLAR PER CMC OCTOBER 2025 PERMIT REPORTResidential$31,899NOT GIVEN2025-10-00171
Jun 25, 2024Solar Energy Device: SOLAR ROOFTOP, BACKUP BATTERY, MAIN PANEL UPGRADE PER 6/24 PERMIT REPORTResidential$31,668NOT GIVEN24-06-00091
Jun 13, 2024Solar Energy Device: INSTALL 16 ROOF MOUNTED SOLAR PANELS AND 1 BATTERY; ADD-ON TO EXISTING SYSTEM PER 6/24 PERMIT REPORTResidential$8,832NOT GIVEN24-06-00087

Heating and cooling: 1 permit

From Jun 4, 2026 to Jun 4, 2026. Fewer than 5 heating and cooling permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Jun 4, 2026Miscellaneous: INSTALLATION OF HVAC SYSTEM PER CMC JUNE 2026 PERMIT REPORTResidential$21,100NOT GIVEN26-06-03028