10
Permits, 24 months
15 on record
4
Roofing permits
Jul 7, 2026
Last permit issued
12
Addresses with a page

Roofing: 4 permits

From Jun 25, 2024 to Mar 9, 2026. Fewer than 5 roofing permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN (3), NOT LISTED.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Mar 9, 2026Roof/Re-Roof: REROOF OF SHINGLES PER CMC MAR 2026 PERMIT REPORTResidential$46,000NOT GIVEN26-03-01173
Dec 2, 2025Roof/Re-Roof: RE-ROOF PER CMC DEC 2025 PERMIT REPORTResidential$53,000NOT GIVEN25-12-05976
May 27, 2025Roof/Re-Roof: PER MAY 2025 MCKINNEY PERMIT REPORT: REROOFResidential$15,000NOT LISTEDRES2025-05-02623
Jun 25, 2024Roof/Re-Roof: REROOF PER 6/24 PERMIT REPORTResidential$12,000NOT GIVEN24-06-03296

Heating and cooling: 8 permits

From Jul 10, 2024 to Jul 7, 2026. Across 6 heating and cooling permits since October 1, 2024, most declared values run from $7,475 to $30,105 (the middle 80%); the median is $10,131 and half fall between $8,680 and $10,497. The lowest on record is $6,709 and the highest $49,634. Filed by NOT GIVEN (8).

IssuedWorkBuildingDeclared valueContractor as filedPermit
Jul 7, 2026Miscellaneous: HVAC PER CMC JULY 2026 PERMIT REPORTResidential$10,262NOT GIVEN26-07-03593
Jun 15, 2026Miscellaneous: HVAC-INSTALL MINI SPLIT PER CMC JUNE 2026 PERMIT REPORTResidential$6,709NOT GIVEN26-06-03212
May 5, 2026Miscellaneous: HVAC-INSTALL 2 COMPLETE SYSTEMS PER CMC MAY 2026 PERMIT REPORTResidential$49,634NOT GIVEN26-05-02372
Feb 27, 2026Miscellaneous: HVAC-REPLACE DOWNSTAIRS 5 TON SYSTEM PER CMC FEB 2026 PERMIT REPORTResidential$10,000NOT GIVEN26-02-00863
Apr 21, 2025Miscellaneous: REPLACE OUTDOOR CONDENSER AND INDOOR EVAPORATOR COIL, PER APRIL 2025 CMC PERMIT REPORTResidential$10,575NOT GIVEN25-04-01917
Nov 21, 2024Miscellaneous: MECHANICAL- REPLACE CONDENSER AND COIL PER 11/24 PERMIT REPORTResidential$8,240NOT GIVEN24-11-06037
Aug 19, 2024Miscellaneous: MECHANICAL- HVAC REPLACEMENT PER 8/24 PERMIT REPORTResidential$10,000NOT GIVEN24-08-04242
Jul 10, 2024Miscellaneous: CHANGE OUT SPLIT SYSTEM PER 7/24 PERMIT REPORTResidential$11,000NOT GIVEN24-07-03549

Plumbing: 2 permits

From Oct 25, 2023 to Nov 15, 2023. Fewer than 5 plumbing permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN (2).

IssuedWorkBuildingDeclared valueContractor as filedPermit
Nov 15, 2023Miscellaneous: TUNNEL SEWER LINE REPAIR UP TO 5FT PER NOV PERMIT REPORTResidential$6,000NOT GIVEN23-6068
Oct 25, 2023Miscellaneous: SEWER SPOT REPAIR UP TO 7FT IN YARD PER OCT PERMIT REPORTResidential$4,000NOT GIVEN23-5639

Solar: 1 permit

From Oct 2, 2024 to Oct 2, 2024. Fewer than 5 solar permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT GIVEN.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Oct 2, 2024Solar Energy Device: SOLAR ROOFTOP, BACKUP BATTERY, MAIN PANEL UPGRADE PER 10/24 PERMIT REPORTResidential$22,302NOT GIVEN24-08-00137