Permits Index
1
Permits, 24 months
6 on record
4
Roofing permits
Mar 3, 2025
Last permit issued
5
Addresses with a page

Roofing: 4 permits

From Aug 23, 2024 to Mar 3, 2025. Fewer than 5 roofing permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below. Filed by NOT LISTED.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Mar 3, 2025Roof/Re-Roof: REROOF PER CPN 2025 MARCH PERMIT REPORTResidential—NOT LISTED25-9171
Sep 19, 2024Roof/Re-Roof: ROOF PERMIT PER SEPT 2024 PERMIT REPORTResidential——24-7380
Aug 30, 2024Roof/Re-Roof: ROOF PERMIT PER AUGUST 2024 PERMIT REPORTResidential——24-7134
Aug 23, 2024Roof/Re-Roof: ROOF PERMIT PER AUGUST 2024 PERMIT REPORTResidential——24-7028

Solar: 1 permit

From Mar 21, 2024 to Mar 21, 2024. Fewer than 5 solar permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Mar 21, 2024Solar Energy Device: SOLAR PERMIT PER MARCH PERMIT REPORTResidential——24-5024

Electrical: 1 permit

From Jul 7, 2023 to Jul 7, 2023. Fewer than 5 electrical permits since October 1, 2024 carry a declared value, so no range is computed; the rows are below.

IssuedWorkBuildingDeclared valueContractor as filedPermit
Jul 7, 2023Miscellaneous: ELECTRICALResidential——23-1700

Addresses on this street with a page

Source

Collin Central Appraisal District building permits, Texas open data, pulled nightly. As of October 1, 2026. Storm dates touching this street will appear here once the hail record is attached.